Understanding Payment Claims Under the CCA
The adjudication, and suspension rights in construction">Construction Contracts Act 2002 establishes a statutory framework for payment claims in construction NZ. When you receive a payment claim, it triggers specific obligations and deadlines that cannot be ignored.
A valid payment claim must identify the construction work performed, the amount claimed for that work, and be served in accordance with the contract terms. The claimant can serve payment claims at intervals specified in the contract, or if not specified, monthly from the first claim date.
You have 20 business days from receiving a payment claim to serve a payment schedule. Miss this deadline and you lose the right to dispute the claimed amount, even if it's wrong.
Your Response Options to Payment Claims
When you receive a payment claim, you have three response options under Section 20 of the CCA:
1. Pay the Full Amount
If you accept the payment claim in full, simply pay the claimed amount by the due date specified in the contract. This is typically 20 business days after receiving the claim, unless your contract specifies otherwise.
2. Serve a Payment Schedule
If you dispute any part of the payment claim, whether the amount, the work claimed, or the entitlement to payment, you must serve a payment schedule. This document must:
- Identify the payment claim it responds to
- State the amount you propose to pay (which can be zero)
- If paying less than the claimed amount, provide reasons for the difference
- Be served within 20 business days of receiving the payment claim
3. Do Nothing (Not Recommended)
If you fail to respond within 20 business days, you become liable to pay the full claimed amount. The claimant can then recover this as a debt, plus interest and costs, regardless of whether the claim was valid.
How to Prepare a Payment Schedule Response
A well-prepared payment schedule protects your position and provides a foundation for any subsequent dispute. Here's the step-by-step process:
Step 1: Review the Payment Claim
Examine the payment claim against the contract requirements and work actually performed. Check:
- Does the claim identify specific work performed?
- Are the quantities and rates correct?
- Is the work complete and compliant with contract requirements?
- Are there any set-off amounts you're entitled to claim?
- Has the claimant met their contractual obligations?
Step 2: Calculate Your Assessment
Determine what amount (if any) you believe is due. This should be based on:
- Work actually completed to the required standard
- Contractual rates and measurement methods
- Any variations properly authorised
- Less any amounts you're entitled to withhold or set off
| Payment Schedule Element | Requirement | Purpose |
|---|---|---|
| Reference to payment claim | Mandatory | Links response to specific claim |
| Amount proposed to pay | Mandatory | States your position clearly |
| Reasons for difference | If paying less than claimed | Justifies your assessment |
| Supporting documentation | Recommended | Strengthens dispute position |
Step 3: Document Your Reasons
If you're paying less than the claimed amount, you must provide reasons. These should be specific and reference:
- Contract clauses that support your position
- Technical standards or specifications not met
- Measurement discrepancies with supporting calculations
- Previous correspondence or instructions
- Set-off entitlements under the contract
Common Reasons for Disputing Payment Claims
Understanding typical grounds for dispute helps you assess payment claims construction NZ projects effectively:
Incomplete or Defective Work
You can withhold payment for work that doesn't meet contract specifications. However, you must identify specific defects and, where possible, quantify the cost of rectification.
Variations Without Approval
Work performed without proper variation approval may not be payable under the contract terms. Check your contract's variation clause requirements carefully.
Measurement Disputes
Quantity disputes are common. Ensure your measurements follow the contract's measurement methodology and retain supporting documentation.
Set-off Entitlements
You may be entitled to set off amounts for liquidated damages, overpayments, or other contract breaches. These must be properly calculated and documented.
Keep detailed records of all work progress, variations, and communications. These become crucial evidence if a payment dispute escalates to adjudication.
Serving Your Payment Schedule Response
Serving your payment schedule correctly is as important as preparing it. The CCA requires service in accordance with the contract terms, or if not specified, by any method that ensures receipt.
Service Methods
- Email: Most contracts now specify email service. Ensure you use the correct email address and request a read receipt
- Registered post: Traditional but slower method. Allow extra time for postal delivery
- Hand delivery: Most reliable method with immediate proof of service
- Contract-specified method: Always check if your contract requires a specific service method
Timing Considerations
The 20 business day deadline is calculated from when you receive the payment claim, not when it was sent. Business days exclude weekends and public holidays. To avoid disputes over timing:
- Serve your payment schedule well before the deadline
- Keep evidence of service (delivery receipts, email confirmations)
- Consider time zones if serving by email to different regions
What Happens After You Serve a Payment Schedule
Once you've served your payment schedule, several outcomes are possible depending on the claimant's response:
Claimant Accepts Your Assessment
If the claimant accepts your payment schedule, pay the scheduled amount by the due date. This resolves the payment claim without further action.
Claimant Disputes Your Assessment
The claimant may initiate adjudication under Section 27 of the CCA. They have specific timeframes to do this, and you'll need to participate in the adjudication process.
No Response from Claimant
If the claimant doesn't respond, pay the scheduled amount. Your payment schedule becomes the final determination of the amount due.
If a payment claim goes to adjudication, you must pay any adjudicated amount immediately, even if you disagree with the decision. You can pursue recovery through later dispute processes if warranted.
Best Practices for Payment Claim Responses
Based on extensive project experience, these practices minimise disputes and protect your commercial position:
Implement a Payment Claim Register
Track all payment claims received with key dates: receipt date, due date for response, amount claimed, and status. This prevents missed deadlines and provides oversight of cash flow impacts.
Establish Review Procedures
Create a systematic process for reviewing payment claims that involves the site team, quantity surveyor, and commercial manager. Different perspectives catch different issues.
Maintain Contemporary Records
Keep detailed records of work progress, quality issues, and variations. Photos, daily reports, and correspondence become crucial evidence in disputes.
Communicate Early and Often
If you identify issues with claimed work, communicate these promptly to the claimant. Early communication often resolves disputes without formal processes.
Calculate Set-offs Carefully
Ensure any amounts you set off against payment claims are properly calculated and documented. Incorrect set-offs can backfire in adjudication.
Provan builds AI-powered operating systems for infrastructure and engineering businesses, covering six domains: Pipeline, Contracts, Projects, People, Finance, and Risk. The Contracts domain tracks every payment claim deadline across your portfolio and maintains a complete audit trail of all claim responses, so you never miss a critical 20-day window. Built from 10 years managing projects from $10M to $750M.
Never Miss Another Payment Deadline
Provan's automated project intelligence eliminates the risk of missed payment schedules and ensures your responses are properly documented and tracked. See how leading NZ construction companies are managing payment claims more effectively.
Book a Working Session